We would like to inform the schedule of mv. Helsinki Bridge, updated as of today. Thanks to favorable weather conditions, the vessel has completed the discharge operation for the damaged empty containers ahead of the schedule posted in the most recent advisory. At this time, pending final inspection and clearance of the vessel at the port, the normal discharging operation can commence. We do sincerely apologize for the overall delay.

 

The most recent schedule is as below:

 

Estimated Schedule mv. Helsinki Bridge 034 (Update as of March 20th 15:00 EDT, subject to change)

 

March 6th The vessel shifted from anchorage to the berth

March 9th Started discharging of damaged empty containers

March 15th Vessel turned to port side alongside to the berth

March 20th Completion of the discharging operation of collapsed containers

March 21st Vessel shift to Wilmington Container Terminal to discharge other containers

March 22nd Completion of cargo operation at Wilmington and will depart to SAV.(*) (**)

 

Again, we regret the inconvenience caused and will keep you posted with any further update.

 

Please note that should you have any questions related to this advisory, you should reach out to ONE directly (1-844- 413-6029), as the Port of Wilmington will not provide any further information to the public at this time.

 

Sincerely, Ocean Network Express (North America) Inc.

8730 Stony Point Parkway, Suite 400

Richmond, VA 23235 www.one-line.com

 

Please click here to download this advisory